Problem
A boutique goat farm needed a flooring solution that would stand up to the concrete corrosion caused by the milk processing process. The facility was only able to suspend operations for 3 days while the goats were milked at a neighboring facility. The facility conditions included wet and milk saturated concrete and a chilling 38 degree temperature.
Solution
DUREX proposed a urethane concrete mortar system. Urethane concrete is moisture tolerant and is able to cure in low temperatures. The quick turnaround time associated with urethane concrete mortars allowed DUREX to return this area to service in less than 3 days.